River Corridor Pipeline, 12km

Otter, water vole and riparian habitat surveys for a 12km utility pipeline route crossing three watercourses.

Location

Yorkshire

Client type

Utilities contractor

Duration

6 months

Outcome

Ecological conditions discharged

River corridor with vegetated banks
Protected Species SurveysHydrology & Water EnvironmentEcological Clerk of Works (ECoW)

01

The requirement

A 12km pipeline route crossing three watercourses required protected species survey and construction-phase supervision to satisfy conditions attached to the consent.

02

The ecology challenge

Otter and water vole were both present along the corridor. The route was still being refined during survey, so the survey area kept moving. This is a common problem on linear schemes and an expensive one if handled by re-scoping each time.

03

Our approach

We surveyed a corridor wider than the proposed route so that refinements stayed within already-surveyed ground, then provided ECoW cover through the sensitive construction phases.

04

The outcome

Surveys completed within programme, conditions discharged without delay to the construction schedule, and no route-change re-surveys were needed.

Result

Ecological conditions discharged

Discuss a similar project →

More projects

Tell us about your project

Send your site postcode, project type and any ecology requirements you have already been given. We will help you understand the next step.